What are the steps to create a work breakdown structure?
Creating a work breakdown structure (WBS) involves several steps. Firstly, one must identify and define the project's major deliverables, which are the final outcomes or products that need to be accomplished. Next, these deliverables are broken down into smaller, more manageable components called work packages. Each work package should be independent, clearly defined, and able to be completed within a specific timeframe. Then, the work packages are further decomposed into activities, which are the specific tasks necessary to complete each work package. Finally, hierarchical numbering is assigned to the deliverables, work packages, and activities in order to create a logical structure that represents the project's scope. This organized breakdown of the project's work provides a clear visual representation of its components, making it easier to schedule, assign resources, and monitor progress.